
Auditor General Nancy Gathungu on September 4 last year /ENOS TECHE
As schools reopen today, top Ministry of Education officials are on the spot for bungling donor-funded classroom projects in primary and secondary schools.
A new audit has cast doubt taxpayers got value for money for the Sh6.7 billion spent by the ministry on the construction works.
Auditor General Nancy Gathungu has in a review of the World Bank-funded project’s accounts cited the managers for breaking the law.
“Full value for money may not have been realised from expenditure on the construction contracts valued at Sh6,655,812,555,” she said.
Gathungu has in the review questioned a spending of Sh60 million on consultants supervising the works in the Secondary Education Quality Improvement Project.
Field visits in Laikipia, Baringo and Homa Bay established that the consultant did not have clerks of work at the project sites.
“The works were ongoing with no evidence of supervision. In the circumstances, the occurrence and accuracy of consultancy services expenditure of Sh60.3 million could not be confirmed,” Gathungu said.
Management, details show, signed agreements with 25 contractors to build 1,506 classrooms, 863 laboratories and 1,932 sanitation facilities.
The audit has cited poor workmanship in some of the projects, which are at various stages, in 30 select counties that had dire space constraints.
“Review of works done on the construction of laboratories for God Bura and Tonga Boys Secondary Schools in Homa Bay County revealed cracked and peeling off of the plastered floors,” the report reads.
Gathungu added, “The gas and water system had not been connected to the laboratories. Although the defects had been noted by the school administration and reported to the contractors, no remedial work had been done.”
The field visit further established that desks, chairs and laboratory chairs supplied to some of the schools were of substandard quality.
Similarly, some of the wooden furniture had splinters and grains and were thus rejected by schools.
The contractor was not on-site at Marigat Integrated Day Secondary School at the time of the audit visit.
“Further, the laboratory was incomplete as electrical wiring and water piping had been done while the floors and walls were cracked,” Gathungu reported.
At the same time, 267 projects in three counties worth Sh344 million had stalled, with the review establishing that 23 per cent of the projects were incomplete.
Tana River County had 67 stalled projects, 186 in Kwale and 14 in Taita Taveta county.
“However, no satisfactory explanation has been provided for the stalling of the projects. There is also no evidence of liquidated damages having been claimed from the contractors while the performance bonds have expired exposing the project to funds loss,” Gathungu reported.
The project’s status and progress report also indicated that 30 classrooms, 40 laboratories, four water projects and 471 sanitation blocks valued at Sh573 million had not been commenced as at 30 June, 2024.
“No explanations were provided for the delay in commencement of the works. In addition, liquidated damages had not been levied by the employer,” Gathungu said.
“Further, termination proceedings had not been commenced despite the contractor having abandoned the work for a period exceeding 28 days without evidence of authorization by the project manager.”
These details have emerged at a time when the government is under pressure to accommodate learners transitioning to Grade 9 and junior schools.
Kenya Primary Schools Heads Association chairman Johnson Nzioka told the Star on Friday that 85 per cent of schools were ready.
“According to reports by our members, the 15 per cent that are not ready have made internal arrangements to accommodate learners as they finish the classrooms,” he said.
Nzioka exuded confidence that most areas have classrooms ready and have also received books at the ratio of one book per pupil.
Auditors established that projects under the extended contracts
remained incomplete as of the end of
the financial year while the performance bonds for the contracts had
expired without renewal