logo
ADVERTISEMENT

State to revive Muhoroni Gas Turbine Power Plant to address blackouts

The plant has been down since June, 2023, due to technical challenges.

image
by FAITH MATETE

Nyanza05 October 2024 - 16:58
ADVERTISEMENT

In Summary


  • The region, with an installed capacity of 249MW, relies heavily on the facility for peak load balancing and grid stability.








Energy Cabinet Secretary Opiyo Wandayi has announced plans to revive operations at the Muhoroni Gas Turbine Power Plant in bid to address the power affecting Western Kenya and parts of Rift Valley.

 

Wandayi noted that the plant, which is crucial to the Western region’s power grid, has been down since June, 2023, due to technical challenges.

 

The region, with an installed capacity of 249MW, relies heavily on the facility for peak load balancing and grid stability, especially during times of high demand or power shortfalls from other plants. 

 

Muhoroni GT is composed of two gas turbines (GT1 and GT2), each with a 30MW capacity, for a total installed capacity of 60MW.

 

"The non operation of this plant therefore has a big impact definitely in the total generation capacity, because 60MW from 249MW, you see the impact is big," the CS noted.

 

The CS, during a fact finding mission at the facility, explained that the ministry is working closely with KenGen, the plant's operator, to revive it as a short term solution to the ongoing outages.

 

"As you know this area, the entire Southern Nyanza region and parts of Kericho and Bomet have had serious power shortages for some time now. Our visit here today is to find out what we can do in the shortest time possible to address this problem."

 

Wandayi highlighted ongoing efforts to expand transmission infrastructure and build substations within the region to curb persistent power outages.

 

The extension of transmission lines includes Thurdibuoro to Ndiwa and Awendo to Isebania and another from Narok to Bomet that will include a substation at Thurdibuoro.

 

"All this transmission infrastructure projects once completed will go a long way in curbing the perennial outages in this region," Wandayi said.

 

The CS added that they are optimistic that the efforts, including the revival of the Muhoroni plant, will mitigate the outages.

 

Kisumu Woman Representative, Ruth Odinga, expressed support for the revival, emphasising its importance to local factories that have been negatively impacted by fluctuating power supply.

 

"The 60 megawatts from this plant will be key to stabilising production and it means more of our people will be accommodated in the factories because now they will be operating at full capacity,” she noted.

 

Muhoroni MP, Koyoo James, lauded the government's efforts to restore reliable electricity supply in the larger Nyanza region.

 

The Muhoroni Gas Turbine originally installed in 1987, was relocated to Western Kenya in phases with GT1 arriving in 2006 and GT2 in 2029.

 

In 2023, the Power Purchase Agreement (PPA) for the Muhoroni Gas Turbines expired on April 30, 2023. 

 

However, the plant continued being dispatched until June 30, 2023, when a decision was made not to dispatch the plant further.

ADVERTISEMENT

logo© The Star 2024. All rights reserved